Most buyers worry about the four-year limitation. The deadline that usually catches them is shorter, and a letter the supplier cannot deny receiving deals with both.

21 November 2026|About 6 minutes|By Han Feng
A hand holding a plain brown envelope over a wooden table

A demand letter to a Chinese supplier restarts the limitation period on the day it reaches the supplier, by courier or by email (Civil Code art. 195; SPC Provisions on Limitation art. 8). The period is four years for an international sale of goods and three for most other claims (arts. 594 and 188). Two shorter clocks often run out first: notice of defects, at the latest two years after receipt (art. 621), and the right to terminate, generally one year after you knew the grounds (art. 564). If time is short, send a written demand today to an address you can prove it reached.

Law as of 20 November 2026: Civil Code of the PRC (effective 1 January 2021), articles 188, 192, 193, 195, 563, 564, 565, 566, 594 and 621; Supreme People's Court Provisions on Several Issues Concerning the Application of the Limitation System in Civil Cases (2008, amended 2020, effective 1 January 2021), articles 2, 4, 8, 11, 14 and 19.

Why the four-year limitation is rarely the deadline that bites

Buyers who ask whether it is too late usually mean the limitation period (the time limit to sue): four years for a cross-border sale of goods, counted from when you knew or should have known of the breach. For an unpaid refund that is usually enough.

The clock that catches buyers is the notice period for defects. If the contract sets an inspection period, a buyer who does not report a quantity or quality problem within it is treated as having accepted the goods (art. 621). With no agreed period, the buyer must report within a reasonable time after finding the defect, and never later than two years after receiving the goods unless a warranty period applies. The exception: a supplier that knew the goods did not conform cannot rely on the notice period.

The second short clock is the right to terminate. Where neither the law nor the contract sets a period, it lapses one year after you knew the grounds, or sooner if the supplier asks you to decide and you let a reasonable time pass (art. 564). Lose it and you can still claim damages, but not undo the contract and ask for the whole payment back.

Where the order had no delivery date and none can be worked out from the contract or trade practice, the limitation starts only when the grace period in your first demand expires (SPC Provisions art. 4). And a Chinese court will not raise limitation on its own; the supplier has to plead it (art. 193; SPC Provisions art. 2).

Thirty thousand dollars, a returned prototype and months of silence

A buyer described this on a public manufacturing forum in April 2026. They had paid a Chinese factory about USD 30,000 to make a collectible plastic toy. The first prototypes were poor, so they sent them back for revision. Since then the factory had not answered for months, although it was still showing the project publicly.

They had sent several follow-ups and formal emails with deadlines and looked for a lawyer without finding practical help. Travelling to the factory was not an option. They asked what they could still do.

If it happened the way they describe, those formal emails may already have done more legal work than the buyer realizes. An email demanding performance interrupts the limitation period once it reaches, or should have reached, the supplier (SPC Provisions art. 8). An email setting a deadline for an overdue main obligation is the warning (催告) that, once a reasonable time has passed without performance, lets the buyer terminate and ask for the money back with damages (arts. 563(1)(3) and 566).

The weak point is proof. Emails sent to a salesperson's personal address, in English, are easy for a factory to say it never received, or never received as the company. And a demand to perform is not yet a termination. The contract ends only when a termination notice reaches the supplier, or when the deadline stated in a notice saying the contract ends automatically has passed (art. 565).

One more question decides which limitation applies. A prototype and tooling job is often a development or processing contract rather than a plain sale of goods, and a court may then apply the general three years instead of four. We would plan on three.

What a demand letter to a Chinese supplier adds to your emails

A letter from a Chinese law firm is written in Chinese, addressed to the company under its registered name, and sent to its registered address and its legal representative (the person registered to act for the company). It goes by a tracked domestic courier as well as by email, so the delivery record shows who signed for it. Signature by the legal representative or the company's mail desk counts (SPC Provisions art. 8).

The letter states the contract, the sums paid and the breach. It sets one deadline. It says that if the supplier does not perform or refund by that date, the contract is terminated without further notice. That last sentence turns the letter into a termination notice that takes effect on its own, and it starts the reasonable time under art. 563 if your earlier emails did not.

Then watch the reply. A supplier that promises a partial refund, asks for more time or offers a payment plan has agreed to perform, which restarts the period again (SPC Provisions art. 14); one that promises after the period has run out cannot later rely on it (Civil Code art. 192; SPC Provisions art. 19). Keep those messages exactly as they arrived.

A letter will not stop a supplier that is already moving its money. Then the next step is pre-suit property preservation, which interrupts the period like a suit does (SPC Provisions art. 11); see our article on freezing a Chinese company's assets. Court or arbitration after that depends on the dispute resolution clause in your contract.

Before the letter goes out, four things a buyer should settle

Find the supplier's registered Chinese name and address first. The name on the PI, the bank account and the website are not always the same company; the national enterprise credit system shows which one is registered and where. A letter to the wrong entity interrupts nothing against the right one.

Write down your dates on one page. A lawyer can tell you within a day which clock is closest once these are in front of them:

Do not let a friendly negotiation run past the notice period. "We will fix it in the next batch" keeps the relationship going, but unless the supplier admits in writing that the goods were defective, the art. 621 period keeps running. Report the defect in writing while you talk.

Do not go public first. Several replies to the post above suggested exposing the factory online. That stops no clock, and a post that goes beyond what you can prove gives the supplier a complaint of its own.

Sources

Frequently asked questions

Related service: Claims Against Suppliers ↗

Has your supplier been silent since your last formal email?

The dispute assessment, USD 590 for one supplier and one order, tells you in writing within 5 business days which time limits apply and what a claim can reach. A demand letter in Chinese and English on the firm's letterhead is USD 950, with the assessment fee credited in full if you instruct it within 30 days.

Related reading

This article is general information on PRC law as of 21 November 2026 and does not constitute legal advice. The answer in any matter depends on its documents and facts.

Han Feng

PRC Lawyer | Tiantai Law Firm Shanghai Office