
To move molds to a new factory in China, first check whether you owe the old factory money that is due. If you do, it may hold the molds, even for a debt from another order in your continuing business (Civil Code arts. 447 and 448; SPC Security Interpretation art. 62). If nothing is due, or your contract excludes a lien (art. 449), you can demand them back (art. 235). If time is short, send a written demand listing every mold and offer security for any disputed amount; a lien ends once the factory accepts it (art. 457).
This article is about the end of a relationship: the tooling has to move, and the factory knows it is losing the business. Who owns tooling in the first place, and what to sign before paying for it, are covered in our articles on mold ownership and paying for molds.
A request to collect the tooling, and a 48-hour deadline in reply
A sourcing company published this account of a client's dispute in March 2024. The client had bought from a Chinese supplier for several years and decided to move. In late July it asked for its tooling to be ready for collection in early August. One order was still open because the supplier had missed a part, and the client said it would pay for that order as normal once it was finished.
The supplier said it was shocked. Its tooling team would first check who owned the tooling (it said it may have paid a small part of the cost), how worn it was and where it was, since tooling was sometimes split among sub-suppliers. That could take a month or more.
When the client asked for a week, the tone changed. The supplier called the request a trick to delay payment. It gave the client 48 hours to pay more than USD 50,000 for the open order, or be reported to the authorities and put on a credit blacklist. It also said it had paid half the tooling cost, which would have to be repaid first. The client had paid the tooling invoices. It had no manufacturing contract.
If it happened the way the account describes, the supplier's position was weaker than it sounded. A lien needs a debt that is due (art. 447), and an order the supplier had not finished is usually not payable yet, though the PO terms decide that. The claim to half the tooling cost needs the supplier's own evidence; the client's paid invoices point the other way.
The blacklist threat was empty too. The list Chinese companies fear, the courts' list of dishonest judgment debtors, covers parties that fail to perform a judgment or other enforceable ruling. A supplier cannot put a buyer on it by complaining.
What the client lacked was paper. A one-page mold schedule, sealed by the supplier and saying the molds would be released on request, would have answered every one of those stalling points.
Can a Chinese factory keep your molds for an unpaid invoice?
Sometimes. A creditor that lawfully holds a debtor's movable property may keep it while a due debt is unpaid (art. 447), and a factory working to order may hold the finished work if it has not been paid (art. 783). The property and the debt normally have to belong to the same legal relationship, but not between companies (art. 448).
The Supreme People's Court narrowed that exception. Where the debt and the molds are not part of the same relationship, the debt must have arisen in the companies' continuing business. And a factory cannot hold a third party's property for a debt unrelated to it (Security Interpretation art. 62).
We test a buyer's arguments in this order. Is anything due, or is the price genuinely disputed because the goods were defective? Does the contract exclude a lien (art. 449)? Do the molds belong to a different company from the one that owes the money? And where the factory holds several separate molds for a small debt, what it keeps should match the amount owed (art. 450), which is the argument for releasing the rest.
A lawful lien still has limits. The factory must look after the molds and pays for damage caused by poor care (art. 451). It must give you at least 60 days to pay before it may sell them or take them in settlement (art. 453). And the lien ends if it accepts other security from you (art. 457). That is why a bank guarantee or an escrow deposit for the disputed amount is often the fastest way to get tooling moving.
Proving the molds are yours before you ask for them back
Assemble the file before the factory hears that you are leaving. The strongest documents are a quotation or PO showing a separate mold fee, the mold invoice and your bank records of payment, a mold list or confirmation sealed by the factory, the T1 sample approval emails, and photos of each mold with its nameplate. A contract clause on ownership and release on request beats all of them.
Two things weaken the file. Tooling paid through the unit price may still belong to the factory until the agreed quantity is reached. And a mold fee paid to a trading company lets the factory say it was never paid at all. If either applies to you, settle what you owe on the molds before you argue about anything else.
Paid in full, so the molds were the buyer's: a Shenzhen retrial
In September 2009 a Hong Kong company ordered 3 million transparent PVC shampoo bottles from a plastics factory in Shenzhen. A separate mold order set the tooling terms: 30% when the molds were opened, the balance once they were approved. It also said the factory would refund RMB 114,000 of the mold cost once all 3 million sets had shipped. The buyer paid the mold fee in full, RMB 264,000.
The relationship broke down in 2010 after 253,000 sets. The buyer sued for its deposits, a penalty and the whole mold fee. The Shenzhen Intermediate People's Court ordered the factory to return about RMB 989,000 of deposits. It refused the mold fee: the refund depended on 3 million sets shipping, and that never happened. But the buyer had paid everything due for the molds, so the court said they belonged to the buyer, which could pursue them through a separate claim ((2012)深中法涉外终字第47号). On retrial, the same court upheld that judgment on 25 December 2017 ((2016)粤03民再43号).
Two lessons for a buyer. A paid mold fee buys the molds, not a refund, so ask for the molds. And the dispute began in 2010; the molds were still a separate fight seven years later. The case was decided under the law before the Civil Code. An owner's right to recover its property now sits in article 235.
Eight molds, one disputed invoice: what the factory may keep
Take a hypothetical buyer that paid USD 48,000 for eight injection molds, USD 6,000 each, under a mold list sealed by the factory. Its last production order has shipped and been paid. A separate USD 9,500 invoice for replacement parts is unpaid, because the buyer says the parts were defective. A new factory is ready to run T1 samples.
If the contract has a no-lien clause, the factory may hold none of the eight (art. 449). The USD 9,500 is a separate argument about defective parts, and it stays that way.
If there is no such clause and the USD 9,500 is genuinely due, the factory can rely on articles 448 and 62: two companies, one continuing business. Even then we would argue that eight molds at cost far exceed the debt, and it may keep only as many as cover USD 9,500, perhaps two, and must release the other six (art. 450).
If the buyer disputes the invoice in good faith, whether anything is due is itself the question, and the lien is weak. But arguing it can take months. Re-cutting eight molds would cost about USD 48,000 and weeks of lead time. Paying USD 9,500 into escrow, or offering a bank guarantee, usually costs less. If the factory accepts, its lien ends (art. 457), all eight molds move, and the parts dispute continues on its own.
If the molds are owned by the buyer's IP company and the invoice is owed by its trading company, the answer changes again: the factory cannot hold one company's property for the other's unrelated debt (art. 62).
One thing we would not do is stop paying an undisputed invoice to put pressure on the factory. That hands the factory a due debt and a lawful lien.
The order we follow when moving molds to a new factory
Pay what is undisputed on time, and get the new factory ready to receive the tooling, before the old factory hears that you are leaving. Then send a written demand in Chinese and English to its registered address and to your usual contacts.
The demand lists every mold by number, states why the molds are yours, names a pickup date and the forwarder, and offers security for any disputed sum. It also asks for last-shot samples from each cavity, so the new factory has a reference for its first trial. Molds leaving mainland China go through export declaration, so bring the forwarder in early.
On the day, have your own QC person or an independent inspector at the factory, and make a handover record.
What to record on the day the molds leave the factory
- Mold number, a photo of the nameplate, the part name and the drawing number
- Number of cavities, and whether every cavity is open and working
- Shot counter reading and date of the last maintenance
- Photos and video of each mold: both halves, cavity and core surfaces, slides, lifters, cooling lines and the hot runner
- Condition notes: rust, cracks, weld repairs, missing inserts or ejector pins
- Items handed over with the molds: electrodes, spare inserts, hot runner controller, 2D and 3D mold drawings, trial and maintenance records
- Last-shot samples from every cavity, bagged and signed by both sides
- Packing: rust protection, crate numbers and weights
- Names, signatures and company chops of both sides, the date and time, the forwarder and the vehicle
If the factory will not sign, write that down and have your inspector and the forwarder sign instead.
If the factory refuses: preserve the molds, then sue for them
Where the molds may be moved, used for someone else's orders or damaged, a court can seal or seize them before any case is filed. You apply to the court where the molds are, where the factory is registered, or a court with jurisdiction. The matter must be urgent, you must give security, the court must rule within 48 hours, and you must start the lawsuit or arbitration within 30 days or the order is lifted (Civil Procedure Law arts. 104 and 106). Our article on freezing a Chinese company's assets explains how preservation works.
The claim itself is for return of the molds (art. 235) and damages, in the court or arbitration your contract names. If the factory has been running your molds for other buyers, that is a further claim; see our article on factories selling overruns of your design.
Sources
- Shenzhen Intermediate People's Court, (2016)粤03民再43号, retrial judgment of 25 December 2017 upholding (2012)深中法涉外终字第47号; text published by the China International Commercial Court at cicc.court.gov.cn/html/1/218/347/329/333/1420.html
- Civil Code of the PRC (effective 1 January 2021), articles 235, 447, 448, 449, 450, 451, 453, 457 and 783, moj.gov.cn/pub/sfbgw/zwgkztzl/2025nianzhuanti/2025mfdxcy/2025mfdxcy_mfdql/202505/t20250507_518708.html
- Supreme People's Court Interpretation on the Application of the Security Provisions of the Civil Code (Fa Shi [2020] No. 28), article 62, court.gov.cn/fabu/xiangqing/282721.html
- Civil Procedure Law of the PRC (as amended in 2023), articles 104 and 106, ipc.court.gov.cn/zh-cn/news/view-6231.html
- Supreme People's Court Provisions on Publishing Information on the List of Dishonest Judgment Debtors (as amended in 2017), article 1, court.gov.cn/fabu/xiangqing/37182.html
- Translations are mine and unofficial.
Frequently asked questions
- How long can a Chinese factory hold my molds before selling them? Unless you agreed otherwise, it must give you at least 60 days to pay, and any sale or valuation must follow market prices (Civil Code art. 453).
- Who pays to ship molds back from a Chinese factory? The contract decides. If it is silent, expect to pay packing and freight yourself; it is rarely worth a dispute.
- Can the factory delay because the molds need checking first? Checking wear or location gives it no right to keep your property. A joint handover record made on collection day covers the condition question.
- Do I need a lawyer in China to get molds back? Not if the factory cooperates. A demand letter from a PRC lawyer helps when it does not, and a court application for preservation or return is filed through PRC counsel.
Related service: Mold & Design Ownership ↗
Before You Sign With a Chinese Factory. A free ten-point checklist for your first production run: five pages, with a tick sheet to print.
Get the checklistMoving production while the old factory still has your molds?
Send us the mold list, the mold invoices and what the factory says you owe. We assess whether any lien applies and the fastest way out, in a written opinion within 5 business days, for USD 590. A demand letter to the factory in Chinese and English is USD 950, with the assessment fee credited in full if you instruct within 30 days. For your next tooling order, a standalone mold and design ownership agreement with a no-lien clause is USD 1,500.
Related reading
- Chinese Factory Won't Return Your Molds? Tooling Ownership and How to Get It Back
- Paying for Molds in China: What to Agree Before the Factory Cuts Steel
- How to Freeze a Chinese Company's Assets Before You Sue: Property Preservation in China
This article is general information on PRC law as of 24 November 2026 and does not constitute legal advice. The answer in any matter depends on its documents and facts.